Park Avenue Viaduct structural replacement finished 60 months early and $195M under budget, Hochul announces
Hochul announced completion of major structural replacement on the MTA's Park Avenue Viaduct: 196 bridge structures and 12,600+ feet of railroad replaced over 28 weekends since October 2023, finishing 60 months ahead of schedule and $195M under the initial $960M budget ($765M project cost), without delaying a train. The 133-year-old viaduct carries 98% of Metro-North service — every train in and out of Grand Central. Remaining track/cable work runs through September 2027.
Related fact-checks
More on transit
Governor's office · Sep 15, 2026MTA issues the RFQ for Contract 4, the last and largest Second Avenue Subway Phase 2 contract: station fit-outs, track, signals, 22 elevators and 20 escalators at 106, 116 and 125 St; RFP by year-end, contractor pick mid-2027, full completion fall 2032 on a $6.968B budgetGovernor's office · Sep 10, 2026Interborough Express: MTA will release the Draft Environmental Impact Statement in Q4 2026, ahead of schedule; all 18 stations to be fully accessible, with ADA work at Broadway Junction, Junius St/Livonia and Ave I due 2026–early 2028 and Wilson Ave contract by mid-2027Governor's Office · Aug 26, 2026Hochul announces service and infrastructure upgrades on the LIRR Montauk BranchamNewYork · Jul 8, 2026Hochul and Mamdani roll out $882M "Next Stop" bus plan; free buses not included
Source: Governor's Office · Jul 27, 2026 · Credibility Tier 1 · Permalink https://reviewhochul.com/news/park-avenue-viaduct-early-completion-jul-2026
ReviewHochul aggregates and contextualizes published reporting. This page links to the original source; it is not a substitute for it.